Dear Members,
As you are aware we have not commenced the construction of the Practice facility due to the inclement weather.
Please find our revised schedule of works.
Thursday 4th April – introduction of the boundary posts on the practice area which will come into play from opening day.
Please note the area is marked with plastic poles these will be replaced with timber boundary posts upon development completion.
The practice area will become an internal out of bounds from 6th April marked by the white posts!!
8th April – Practice Area will be closed and Trackman studio made available to members free of charge during this period via booking in the Professional shop subject to availability.
Monday 8th-Friday 12th April – Tree Surgery Commences – 10,000 Titleist range balls arriving & 2000 Pro V1’s land.
Monday 15th Ground works commence on Practice area – timeline 3 weeks completion.
Monday 29th April Range Construction commences & ball dispenser and washer installation
May 6th Huxley Greens installed & works competed 20th May
Facility Opening Mid June.
Fingers crossed 🤞
Regards,
James Erskine
Club Professional